Gateway Deployment Projector
Field Service Tech capacity planning · 6 gateways/hour at 10 min/unit · 2 gateways/site across 60 sites
Deployment Scope
units to deploy
units
locations / addresses
sites
Avg gateways / site2
Workforce
field service techs
FSTs
per FST
hrs
scheduling
days
Install Time
8–12 min typical
min
Throughput6 / hr
48 units/FST/day at 8h on-site
Projected Completion
Wed, Mar 25, 2026
1 working day · 0.2 weeks · starting today
Gateways / Hour
6
at 10 min / unit
Units / FST / Day
48
8h on-site
Total Install Hours
20h
across 4 FSTs
FST-Days Required
0.6
total labor-days
Total Sites
60
2 gateways / site
Working Days / Week
5
960 units/week total
FST Utilization63%
Under-utilized — consider fewer FSTs or a shorter engagement
Calculation Model
Gateways / hour60 min ÷ 10 min = 6/hr
Units / FST / day6/hr × 8h = 48 units
Total install hours120 units ÷ 6/hr = 20h
Calendar days120 units ÷ (48 × 4 FSTs) = 1d
Total sites120 gateways ÷ 60 sites = 2 avg/site